Frank continued on with the dry wall. He worked clockwise around the center hexagon, stopping to make the walls for the different rooms as he came to them. He finished the bathroom.




















Then he made the kitchen wall.




He went on to the pantry/laundry room. He reinstalled the laundry sink. He also put up the
cover for the corner.





















Next was our bedroom. This involved the closets as well.

















By Tuesday last week, I went back to sanding and applying the finish to the tongue and groove boards for the great room ceiling. I didn't work hard or long, but did do a little each day. All of the T& G now have one coat of finish on them, and I am starting on giving them a second coat. The main difference : I am now wearing a mask.

















Here is Frank using his dry wall lift. One more day and he will be finished with the dry wall.